CafesideMTB Planning Updates

Planning Update August 2024

We are currently awaiting Teignbridge District Councils decision on our second planning application. Following discussions with planning consultants and the new UK MTB Trail Alliance, we decided to apply for a Certificate of Lawfulness for Existing Use (CLUED) to obtain change of use on the site from Forestry to Forestry and Mountain Bike Trail Centre, and protection under Permitted Development to cover the building and maintenance of both existing and future trails on the site.

The CLUED application requires the site to have been in constant use for over 10 years, so we have supplied YouTube videos, photos, race events and details from Forestry England supporting our application.

The Permitted Development Rights are related to the fact that CafesideMTB is on Crown Land, and as a group CafesideMTB have been and will continue to be working with and on behalf of Forestry England. Being on Crown Land offers a range of development rights that mean we will not have to apply for additional planning permission for new trails, features etc. when building in future.

Planning Update March 2024

We’ve been asked by Teignbridge District Council planning department to withdraw our planning application otherwise it will be refused in its current form.

The issue is with the boundary of our planning application. Back in September 2023 we submitted our initial planning application with the boundary covering the entirety of the Cafeside site - the car park, start ramps plus the whole of the plantation to cover all the trails.

At this point our application was received but missed by the planning department, and after 3 months of chasing, eventually entered the validation process. “Something appears to have gone wrong” was the reason given for this delay.

On the advice of the Teignbridge District Council planning department during the validation phase, they recommended that we updated the boundary drawing so that it was under 1 hectare, covering the car park and start ramps.

We have now been advised that they want the boundary line to cover the entire site after all, allowing the commercial woodland to have change of use so that it becomes “commercial woodland and mountain bike trail centre”.

To get to this point 6 months after submitting our application is frustrating beyond words. Having gone through this in detail with Teignbridge District Council planners, they will not permit us to update our existing application, nor will we be getting a refund on the fees we paid. “We tried to be helpful, but unfortunately we got this one wrong” was their explanation.

We can appeal, but this would take up to 32 weeks, and again, would only give us planning for the car park and start ramps, not the change of use needed to allow us to alter and expand the trail network going forwards.

Therefore we will be withdrawing our planning application, amending the drawings and document to take into account all of the feedback that we’ve received during the last 6 months of the planning process. We will then re-submit as soon as possible.

We are as frustrated as anyone that this is the situation that we’re faced with, but we’re not going to give up. We’re confident that going forwards our revised application will be stronger, and hopefully this is a speed bump on the road to getting Cafeside re-opened.

Once we have our new planning application live, we’ll be asking everyone to re-submit their letters of support, as these can not be carried over from the first application. Yes, we asked...

CafesideMTB planning timeline

8th September 2023: Planning submitted but “missed” by TDC.
September to December
2023:
Emailing and phone calling TDC to try and work out what’s going on.
1st December 2023: Planning now found & validated by TDC, changes required, amend boundary from full site to the car park / start ramp area, provide surface water management plan.
15th December 2023: Updated planning application and relevant documents submitted.
15th December 2023: Updated planning application passes validation.
Planning application on the TDC planning site.
December to Febuary
2024:
Over 120 letters of support submitted - Amazing, thank you everyone!
9th January 2024: Attended Kenn Parish Council meeting to discuss our planning application with the councillors and the attending public.
25th January 2024: Met Senior TDC Planning Officer and Archeologist on site to discuss application and show them the proposed car park / start ramps and existing trails.
30th January 2024: Additional documents submitted to TDC planners covering KPC concerns and Nightjar Plan
23rd February 2024: Notified by email of TDC planning officers wish for us to withdraw our application.
6th March 2024: Phone meeting with planning officers to try and resolve.
8th March 2024: CafesideMTB CIC board meeting to discuss withdrawing and resubmitting rather than appealing. This was the agreed way forward.
April 2024: Following discussions with planning consultants and the new UK MTB Trail Alliance, we decided to apply for a Certificate of Lawfulness for Existing Use (CLUED) and protection under Permitted Development to cover the building and maintenance of trails on the site.
28th May 2024: CafesideMTB submitted their CLUED application to Teignbridge District Council, which passed validation and was opened to public consultation on the TDC planning website.
4th July 2024: Public consultation closed on our application.
9th July 2024: CafesideMTB CIC attended Kenn Parish Council's monthly council meeting to discuss our application with the councilors and answer any questions they had etc.
19th July 2024: CafesideMTB CIC met our TDC Planning Officer on site to show them the trails that we're still maintaining and test riding, answer any questions, provide trail plan etc.
23rd July 2024: Expected decision date for our application. We are led to believe by our Planning Officer that a decision has been made, however we are still awaiting the result of the decision to be made public at present.